| Objective 1 – To develop a strategic network of safe, convenient and continuous cycle routes in the Borough, including links with adjacent cycle networks and utilising footpaths, bridleways and roads where appropriate |
ActionTimescaleResponsibility
(Involvement) |
| 1. Agree a core strategic network of routes (see Annexe 6) and keep under reviewReview annuallyWCF/WBC/SCC |
| 2. Identify key destinations (e.g. public transport interchanges) and establish a target for increasing accessibility over the period of the PlanBy March 2005WCF/SCC |
3. Prioritise locations which have been identified as barriers for cyclists (e.g. the A3 and A31) and prepare a programme of action to overcome those barriersOct 2004 & review annuallyWCF/SCC
(T&PC’s) |
| 4. Develop links with cycle fora in adjacent Boroughs/Districts to ensure continuity of cross-boundary routesOngoingWCF |
| Objective 2 – To safeguard, maintain and enhance the strategic cycle network |
| ActionTimescaleResponsibility |
| 1. Carry out a cycle audit on all significant highway improvement and maintenance schemes and then consult the Forum to obtain best value for cyclistsOngoingSCC |
| 2. Define a co-ordinated approach to maintenance and ensure that on and off road cycle tracks are included in future maintenance programmes2004, ongoingWCF/WBC/SCC |
| 3. Submit revised Waverley Cycling Plan to the SCC ‘Waverley Local Committee’ to raise awareness of the strategic networkBy March 2005WBC/SCC |
| 4. Contribute to development of guidelines on appropriate forms of surface treatments, especially in environmentally sensitive areas2005WCF/WBC/SCC |
| Objective 3 – To improve the safety and accessibility of the town centres of Farnham, Godalming, Haslemere and Cranleigh to their adjoining residential areas and villages |
ActionTimescaleResponsibility
(Involvement) |
1. Liaise with town and parish councils to prioritise new routes and other improvementsCommence 2004; ongoingWCF/WBC/SCC
(T&PC’s) |
| 2. Promote cycle access as part of all developmentsOngoingWBC/SCC |
3. Forum to appoint representatives for each of the main population centres in WaverleyAnnually (each January)
WCF |
| Objective 4 – To participate in the County-wide Safe Routes to School (SRS) initiative |
ActionTimescaleResponsibility
(Involvement) |
| 1. Consult the Forum on all SRS schemes in WaverleyOngoingSCC |
2. Provide information and advice to local schools on safe routes, ‘cycling buses’ etc (e.g. through use of WBC/SCC websites)OngoingWCF/WBC/SCC
(T&PC’s) |
| 3. Adopt SRS routes into the strategic network and include in future maintenance programmesOngoingWBC/SCC |
| Objective 7 – To link the Borough to the National Cycle Network (NCN) |
| ActionTimescaleResponsibility |
| 1. Define NCN Route 22 as it goes through WaverleyBy end 2004WCF/WBC/SCC |
| 2. Press for upgrading of the Downs Link to NCN standards and investigate its adoption as part of the Regional Network2005WCF/WBC/SCC |
3. Investigate possibility of a spur from NCN Route 22 to link Godalming and Guildford
2005WCF/WBC/SCC |
| Objective 8 – To improve the quantity, quality and security of cycle parking facilities at convenient locations |
ActionTimescaleResponsibility
(Involvement) |
| 1. Review current adopted standards for cycle parking provision in new developmentBy end of 2005WBC/SCC |
| 2. Improve monitoring of planning applications and enforcement of conditions relating to cycle parkingOngoingWBC |
| 3. Forum to review cycle parking in Waverley and identify gaps in provisionAnnually (each April)WCF |
4. Liaise with Surrey Police to find out locations where bikes have been stolen Annually (each April)SCC
(Surrey Police) |