ACTION PLAN | BY WHOM | BY WHEN [month = by month end] | BUDGET IMPLICATIONS | PROGRESS | REVISED TIMETABLE | SAVINGS |
 |  |  |  |  |  | £000 |
TARGET 2: Formal Policies And Procedures For Delivery Of Programmed And Cyclical Maintenance Service With Particular Emphasis On:
· customer service
· health and safety
· efficiency
· value for money |  |  |  |  |  |  |
Develop a strategy to increase the balance of expenditure on repairs and maintenance in favour of planned maintenance Common action point with Day-to-Day Repairs | Head of Housing Maintenance | December 2002 | Within existing budgets | Done | Done | Not yet quantifiable |
Identify customer profile and obtain feedback about their priorities for improving the service | Service Review Group | December 2001 | As above | Done | Done | 0 |
Formalise and document process for involving Tenants’ Panel in development of annual and five-year programmes of planned maintenance | Head of Housing Maintenance | September 2002 | As above | Introduced in 2001/02 and now repeated each year | Done | 0 |
Develop code of practice for contractors in consultation with Tenants’ Panel covering all aspects of programmed and cyclical maintenance service | As above | September 2002 | As above | Ongoing – first priority has been code of practice for repairs contractors | March 2004 | 0 |
In consultation with contractors and Tenants’ Panel, develop appointments system for visits by contractors and staff to tenants’ homes where access is required | As above | June 2002 | As above | Implemented as appropriate | Done | 0 |
Introduce procedures for consulting all tenants and leaseholders who are going to be affected by programmed and/or cyclical works and providing choice over finishes wherever possible | As above | September 2002 | As above | Done | Done | 0 |
Introduce systems for paying compensation to tenants for any failure to meet the Right to Repair requirements in relation to repairs to gas heating systems | As above | September 2002 | As above | Better information regarding Right to Repair included in Tenants’ Handbook | February 2003 | 0 |
Develop and adopt recording, monitoring and reporting systems for customer complaints that are compatible with Departmental and corporate procedures | As above | May 2002 | As above | Departmental system implemented for complaints. | Done | 0 |
Produce policy and implementation plan for dealing with asbestos and any known other risks that includes a strategy for appropriate:
· action to be taken to determine the nature of the risk
· information to be disseminated to tenants, contractors, staff and any other affected parties
· action to be taken to make safe Common action point with Day-to-Day repairs | As above | April 2002 | As above | Policy agreed by Executive in spring 2002. Implementation plan/strategy being developed | Policy done. Implementation plan/strategy – November 2002 | 0 |
Re-examine and clarify roles and responsibilities of Surveying and Maintenance and Day-to-Day Repairs staff with a view to further streamlining and generalising functions where possible and appropriate Common action point with Day-to-Day repairs | Head of Housing Maintenance | March 2004 | Within existing budgets | Relocation of S&M to Godalming has improved liaison & co-operation. Structure to be reviewed when MTC due for renewal | Done in part. Structure to be reviewed by March 2005 | 0 |
Complete documentation of policies, procedures and guidelines for all aspects of programmed and cyclical maintenance service and introduce arrangements for regular review | As above | October 2002 | As above | Consolidation of policies/procedures ongoing | April 2003 | 0 |
TARGET 3: Improved Information For Customers |  |  |  |  |  |  |
In consultation with the Tenants’ Panel, produce leaflet(s) explaining in plain English:
· the service aims, objectives and standards
· key policy issues
· how the annual programme of works is developed | Head of Housing Maintenance | September 2002 | Within existing budgets | Articles in Waverley Homes about planned maintenance service.
Information on planned maintenance in Tenants’ Handbook.
Discussions taking place with Tenants’ Panel about what else is required.
Production of leaflet (if required) | June 2002
February 2003
November 2002
September 2003 | 0 |
Give the leaflet(s) to all existing and new tenants | As above | As above | As above | Despatch (if produced) | April 2004 | 0 |
Ensure that tenants are aware of the Right to Repair provisions in relation to repairs to gas heating systems | As above | May 2002 | As above | Information about Right to Repair included in Tenants’ Handbook | February 2003 | 0 |
Publish a summary of the annual programme of programmed and cyclical maintenance works that have been approved by the Council in Tenants’ Extra so that all tenants are aware of what works will be taking place and in which area. Send details to leaseholders. | As above | June 2002 and ongoing | As above | Information included in summer 2002 issue of Waverley Homes
Format for more detailed information to be agreed with Tenants’ Panel and leaseholders | Done in part
Further details of programme to be published by March 2004 | 0 |
Provide all tenants and leaseholder who will be directly or indirectly affected by programmed and/or cyclical works with detailed written information including:
· proposed timetable for works
· likely disturbance
· code of practice for contractors
· identity of contractors
· contact point for complaints and enquiries
· commitment to keep residents informed about start/finish dates | As above | May 2002 and ongoing | As above | Done | Done | 0 |
Ensure residents affected by works are informed about any delays or changes to the timetable for the works | As above | Ongoing | As above | Done | Done | 0 |
Consult the Tenants’ Panel on the performance information to be provided about the service | As above | July 2002 and ongoing | As above | Ongoing | April 2003 | 0 |
Include regular articles in Tenants’ Extra on those aspects of performance identified as priorities by Tenants’ Panel | As above | Ongoing | As above | Ongoing | April 2003 | 0 |
TARGET 4: Improved Stock Condition Information Available To All Housing Staff
|  |  |  |  |  |  |
Investigate and report on the range of stock condition data that is needed and can be made available on Orchard (integrated housing management system) | Head of Housing Maintenance | May 2002 | Within existing budgets | Depends on relating Decent Homes data to property addresses | April 2004 | 0 |
Determine contents and format of database of stock condition information that is capable of being directly input or downloaded onto Orchard | As above | July 2002 | As above | As above | As above | 0 |
Input existing data onto Orchard | As above | December 2002 | As above | As above | As above | 0 |
Develop plan and timetable for gathering additional stock condition data including using staff routinely visiting properties | As above | September 2002 | As above | Ongoing | Target to gather 25% of data by April 2003 and remaining 75% by April 2004 | 0 |
Draw up pro-forma for staff to use to gather stock condition data | As above | As above | As above | Resources being investigated to gather data | December 2002 | 0 |
Investigate use of hand-held computers and/or other systems to enable gathering and inputting of stock condition data to be carried out as efficiently as possible | As above | As above | As above | As above | As above | 0 |
Staff to gather stock condition data during visits to properties and input data onto Orchard using most efficient and cost-effective method available | As above | April 2004 | As above | MicroSurvey will be used to analyse data which will eventually be downloaded to Orchard | April 2004 | 0 |
TARGET 5: Maximising Use Of IT And Working Towards E-Government Targets Common target with Day-to-Day Repairs and Voids Management – see Improvement Plan relevant to All Housing Services
|  |  |  |  |  |  |
Develop strategy for future use of IT within Surveying and Maintenance Section | Head of Housing Maintenance | April 2002 | Within existing budgets | Done | Done | 0 |
Draw up plan and timetable for implementation of Orchard and transfer of data currently held on Access databases to it | As above | As above | As above | Ongoing | Implementation of Orchard to be completed by March 2003 | 0 |
Where existing Access databases are to be retained examine ways in which they can be streamlined | As above | September 2002 | As above | Ongoing | Ongoing | 0 |
Investigate ways of creating further linked IT systems with contractors where appropriate | As above | Ongoing | As above | Done where appropriate | Done | 0 |
TARGET 6: Robust Systems For Improved Performance Management Systems For Monitoring Quality And Efficiency Of Service
|  |  |  |  |  |  |
In consultation with the Tenants’ Panel introduce mechanisms and/or enhance existing systems to obtain regular detailed customer feedback on the service including troduce comprehensive satisfaction monitoring, analysis and reporting for all aspects of the programmed and cyclical maintenance service including repairs carried out to gas heating systems, “mystery shopping” exercises etc. | Head of Housing Maintenance | September 2002 | Within existing budgets | Done | Done | 0 |
Introduce systems for monitoring, analysing and reporting whether appointments have made and kept in relation to repairs to gas heating systems | Head of Housing Maintenance | May 2002 | Within existing budgets | Investigated – could not be done as part of existing contract | To form part of new contract due for renewal June 2003 | 0 |
Develop systems to analyse information provided through complaints to identify issues and trends relating the quality of the service | As above | As above | As above | Done | Done | 0 |
TARGET 7: Contract Arrangements For Programmed And Cyclical Maintenance That Ensure Quality Of Service And Value For Money |  |  |  |  |  |  |
Pilot an area of programmed or cyclical works on partnering basis (in accordance with Egan/”Rethinking Construction” principles) | Head of Housing Maintenance | March 2003 | Within existing budgets | Ongoing. Half of external decorations 2003/04 contract to be piloted on partnering basis | Implementation March 2003 | Not yet quantifiable |
Evaluate partnering contract against conventional contract in terms of value for money, quality of work and customer satisfaction | As above | As above | As above | As above | As above | 0 |
Investigate and where possible introduce a Schedule of Rates type of approach to other programmes of work including external decoration | As above | As above | As above | Ongoing | Ongoing | Not yet quantifiable |
Involve Tenants’ Panel in selection of contractors | As above | As above | As above | As above | As above | 0 |
Seek Members’ approval to add Repairs MTC contractors to Programmed & Cyclical works standing list of contractors | As above | As above | As above | Done | Done | Not yet quantifiable |