Meeting of the Executive held on 09/07/2002
East Street Regeneration Scheme



ANNEXE 1

East Street Regeneration Scheme

Extended Programme of Meetings 2002/03

• 27th May 2002 - Joint O&S meeting to consider process


• 11th June 2002 - Executive – to consider process


• 9th July 2002 - Executive – to recommend Council
on criteria weighting


• 15th July 2002 - Closing date for submission of bids


• 23rd July 2002 - Council-ratification of criteria


• 16th Sept 2002 - O&S – observations on selection of partner



• 30th Sept 2002 - Executive – agree recommendation to Council on
favoured partner


• 15th Oct 2002 - Council – agree partner and confirm
instructions to lawyers


• 30th Jan 2003 - Target date for exchanging contracts
(provisional)




Version 2 for Exec 09/07/02

Comms/exec/2002-03/112