IMPROVEMENT REQUIRED (1) IMPROVE SCOPE AND EFFECTIVENESS OF ENFORCEMENT SERVICE |
No.Actions Required to Achieve
ImprovementEvidenceBy WhomBy WhenResource
ImplicationsProgress: April 2002 |
DC1Employment of Enforcement Manager and additional administrative supportConsultation
Benchmarking
ChallengeDCPM/PPDec.
2001Annual
Enforcement Manager £51,688 p.a. inclusive of notional costs of £12,953
Admin Assistant £7,806 p.a. inclusive of on-costsResource has been included in 2002/3 budgets.
New structure is to be considered by Council 23rd April 2002. |
DC2Introduction of new IT system for maintaining Enforcement recordsConsultation
ChallengeBI&SMJuly 2001Setting up
2 days programming time within existing resourcesSystem in place October 2001. However, whilst an improvement it is well short of delivering service improvements required by the DCPM. There is still a need to develop an integrated system with other applications/cases.
Test systems installed. Project Plan being developed with suppliers. |
DC3Publication of leaflet setting out information regarding the Enforcement Service, together with the Charter standardsConsultation
Benchmarking
ChallengeDCPM/PPDec. 2001Setting up
£100 to be met from existing print budget. 2 days staff time in writing and designDevelopment Control Charter now agreed and published on the web site.
Work has commenced on a suite of charters designed for particular client groups, including those interested in the enforcement service. |
IMPROVEMENT REQUIRED (2) IMPROVE THE ACCESSIBILITY OF THE SERVICE AND INFORMATION TO CUSTOMERS |
No.Actions Required to Achieve ImprovementEvidenceBy WhomBy WhenResource ImplicationsProgress: April 2002 |
DC7Make available all current planning applications, including plans and drawings, on the web-siteConsultationBI&SMApril 2002Setting up and Annual
Costs included in capital programme budget for Information Management Progress dependent on implementation of new IT systems and integration between DIP and new planning systems.
Work has commenced on imaging systems and integration with application processing systems. |
DC8Make available all planning forms on the web-siteConsultationBI&SMDec 2001Setting up
4 hours setting up time. Within existing resourcesWork in progress |
DC9Publish history and constraint information on the web-siteConsultationBI&SM2003Setting up
Costs included in capital programme budget for Information ManagementWork not commenced. |
DC10Improve Planning Reception facilitiesConsultationBI&SMDec. 2001Setting up
£25,000
Resources to be allocated in 2002/3 budgets. Report to Executive anticipated in May/June |
DC11Provide Locality Offices with access to Planning IT facilitiesChallengeBI&SMDec. 2001Setting up
Staff training and set up time – minimal costsWork in hand and anticipated target will be met. Need to build in training for Locality Area staff. |
DC12Introduction of Duty Officer scheme for Planning receptionConsultationPPSept. 2001Annual
150 hours. (Based on an estimated 3 hours per week). It is hoped that costs will be contained within existing resourcesCommenced. |
DC13Publish additional information literature to include the following: -
1. Pre-application advice
2. Handling “Permitted Development” enquiries
3. Submission of a planning application
4. Amendments to applications
5. Making representations on planning applications etcConsultation
ChallengeDCPM/PP/BI&SMOngoing programme 2001-2002Setting up
10 days staff time (2 per leaflet)
£500 design cost from existing print budget.
Annual
£500 from existing budget.Draft list of tasks and priorities produced. Work commenced on
· general Householder enquiries,
· Representations on planning applications,
· Charters
· Enforcement policy |
DC14Introduce revised arrangements for keeping applicants informed on progress of planning applicationConsultation
ChallengeDCPM/PPSept. 2001 Nil costCommitment to keep applicant informed introduced. This now needs to be backed up by guidance notes, charters and performance management systems. |
DC15Introduce arrangements for the early identification of case officer for planning applicationsConsultation
ChallengeDCPM/PP
BI&SMJuly 2001Nil costCommenced. Officer identified on acknowledgement letter. |
DC16Introduce arrangements for notifying objectors of the outcome of an applicationBenchmarking
ConsultationDCPM/PP
BI&SMNov. 2001Annual
Dependent on
take-up. It is hoped that costs will be contained within existing resourcesActioned 1st November.
This will assist enforcement monitoring process with better-informed neighbours re the terms of planning permissions. |
IMPROVEMENT REQUIRED (3) DESIGN AND MANAGE THE SERVICE TO MEET CUSTOMER REQUIREMENTS AND PERFORMANCE TARGETS |
No.Actions Required to Achieve ImprovementEvidenceBy WhomBy WhenResource ImplicationsProgress: April 2002 |
DC17Introduce revised Charter for Development ControlChallengeDCPMSept 2001Setting up
3 days staff time.
Annual
£100 print costs from existing print budget.Completed. (See DC3 and DC 4) |
DC18Adoption of Development Control Procedure ManualChallengeDCPM/PP
BI&SM Sept. 2001Annual
It is hoped that any additional costs in terms of staff time can be contained within existing resourcesDraft procedures now produced. These now need to be tested and worked through by staff responsible for their operation.
It is proposed to create a working procedure manual on the server enabling officers and members to access from PC’s and perform searches.
This needs to be developed in parallel with new IT systems |
DC19Reduce backlog of applications awaiting registration and introduce arrangements or new applications to be logged on the computer system on day of receiptConsultation
ChallengeBI&SMCompletedCompletedEarly warning system introduced end November to identify increases in workloads or productivity issues. |
DC20Adoption of Action Points emerging from review of proceduresChallengeDCPM/PP
BI&SMOngoingSetting up
30 hours staff time. Within existing resources.Copy of Action Plan attached as annexe 3 |
DC21Integration of Administration Team and Development Control Team and restructuring into two area based teamsChallenge
ConsultationBPDMSep 2001There will be minor cost implications both in terms of setting-up costs and annual costs, but it is anticipated that these can be contained within existing budgets. This matter will be the subject of a further reportReport to Council in April re new establishment. |
DC22Introduction of new/upgraded planning systemConsultation
ChallengeBI&SMApril 2002Setting up
Capital scheme included in 2001/2002 £28,000SeeDC2 |
DC23Establish programme for Staff and Member trainingConsultation
ChallengeDCPM/PP/BI&SMDec. 2001Setting up
2 days staff time to establish.
It is hoped to keep any ongoing costs within existing resourcesStaff training programme commenced with Away Day for Senior Officers.
Appraisal training 9/11/01. Appraisals to be carried out during November with training needs identified.
November /December design training.
DCPM to prepare training and development plan for service following completion of appraisals. |
Member training and development opportunities were raised at the special event and to be considered by Planning Services SIG on 15th April 2002 |
DC24Assessment of whether elements of the service can be outsourcedCompeteDCPMDec 2003Unknown at presentThis needs lateral thinking e.g. Neighbours and Town/Parish Councils to be eyes and ears re implementation.
Getting landowners and developers to prepare planning briefs.
Can we get other organisations working for us e.g. police?
Partnerships with other Surrey or adjoining Authorities e.g. sharing of strategic work /issues.
Use of authority pool of labour for periods of high activity?
Joint funding of specialist skills e.g. Telecommunication techno babble. |
DC25Work towards integration of all appeals administration within Planning SectionChallengeBI&SMSept 2002Possible savings. Subject to further reportBring forward and implement as part of organisational change in may 2002 |
 |  |  |  |  |  | DCPM view is that this review should be brought forward as there is considerable energy consumed in current practices. It could also be important key to releasing resources into other areas e.g. enforcement.
There are also paradoxical concerns from the DCPM that the delegation scheme is too wide and vague and does not have appropriate checks and balances to comfort Officers or Members in its operation. E.g. What is small scale? What is meant by clearly in conflict with the Council’s policy when applied to say issues of streetscene?
Planning Services SIG to consider discussion paper in May 2002 |
DC32 | Introduce use of improved facilities for displaying plans and other information at Committee meetings | Consultation
Challenge | DCPM | Dec 2001 | Setting up
2 digital cameras already purchased. Additional storage of images.
Annual
24 days staff time. (Based on ½ day preparation time per Sub-Committee meeting. It is hoped that these costs can be contained within existing resources | Work Commenced.
Pilot presentation to DC Committee in September. Following feedback work has commenced on logistics and equipment to service all area committees.
Unlikely to meet December target. New target was sub committee meeting in January 2002 but technical and resource issues meant this floundered.
Additional digital cameras have been ordered to enable officers to records sites during their routine site visits and avoid multiple visits.
Work has commenced on imaging systems. However, capturing of plans and information will reduce micro filming costs.
Projector and screen options being investigated as appropriate to each venue. |
 |  |  |  |  |  | Alternative venue for Southern Area Sub-Committee being investigated. |
DC33 | Investigate possible establishment of an Architects Panel | Challenge | DCPM/PP | Dec 2003 | Subject to further review | To be done. |
IMPROVEMENT Proposed Shift priorities from a purely policy making role to developing and delivering detailed policy guidance, information, monitoring and action |
No.Actions Required to Achieve ImprovementEvidenceBy WhomBy WhenResource ImplicationsProgress: November 2001 |
PIE 1Devise and Implement Programme for preparation of SPGConsultation
Challenge
ComparePP/PEO/
ECO/SPA/
TLODec 20032 FTE for two years within existing budgetDraft programme prepared and priorities identified. |
PIE 2Devise and Implement Programme for preparation of Advice and Information notesConsultation
Challenge
ComparePP/PEO/
PIO/HBODec 20032 FTE for two years within existing budgetDraft programme prepared and priorities identified. |
PIE 3Devise new and refine existing monitoring programmesConsultation
ComparePP/PEO/
PIO/ECO/
SPA/PTCommence work May/June 2001 then ongoing.New IT software.Work commenced but progress limited. |
PIE 4Adoption of Planning Users ConcordatConsultation
CompareDCPM /PPDec 20011 week within existing budget.Document drafted. |
PIE 5Investigate areas for greater inter authority liaison with Best Practice Group, Benchmarking Partners, Blackwater Valley Network and neighbouring Authorities.Compete
ChallengePP/ECO/PT Ongoing10% FTE within exiting budgetWork commenced on Blackwater Valley study.
SPOA investigating joint working.
County -wide design training completed following drafting of Surrey Design Guide.
Highway Liaison meetings arranged |
 | ACTION PLAN | WHO | TIMESCALE /COMMENT ON PROGRESS |
1. | HOUSEKEEPING:
Space Creation – files out
keep active files only
Layout Plan
Furniture | DCO/LN
LN |
complete
microfilming still to be done
office move – 04/01/01 COMPLETED |
2. | FILE ACCESS
Feedback exercise
Queries vs Plans
| LN/PT | Sample exercise carried out on use of historic files – decision to retain for 5 years.
image processing – alternative process to be discussed with Phil Tucker. Information scanning – trial to be set up on site – END OF JUNE.
(Not met. This is now part of a larger picture re DIP’s and file management, which is under consideration.) |
3. | DATE STAMP |  |
Self inking date stamp to the design required not available |
4. | REGISTRATION AT POINT/TIME OF RECEIPT | LN |
COMPLETED |
5. | PRINTED ENVELOPES
Investigate corporate print | LN/BT |
|
6. | ENVELOPE STUFFER | LN |
COMPLETED |
7. | SITE NOTICE ETC.
Print directly
Templates | LN |
Dependent on new IT system implementation.
|
8. | DOCUMENT DATA CONTROL PROCEDURE | JB/LN | To be actioned as part of new organisational arrangements. |
9. | INFORMATION SHEETS/MAPS ACCESS/COMMONS
Talk to BELM | LN |
Work in hand and will meet Local Plan adoption timetable. |
10. | WEEKLY LIST
Reorganise | LN/PT | COMPLETED |
11. | USE OF MKA BY OFFICERS – Training
Reports ? | LN/BT | COMPLETED |
12. | REPORT TEMPLATES | BT | COMPLETED |
13. | FILE MAINTENANCE
Programming Fix | LN | Now agreed to be resolved as part of upgrading of IT software. |
14. | INTERNAL TARGETS
Development and training | ST/
BT/LN |
Staff training programme commenced with Away Day for Senior Officers.
Appraisal training 9/11/01. Appraisals to be carried out during November with training needs identified.
November /December design training.
DCPM to prepare training and development plan for service following completion of appraisals.
Member training and development opportunities to be raised at special event and Planning Services SIG
|
15. | AMENDED PLANS
Agree with APO
Procedure Item | ST/BT |
Procedure now in operation. Flow chart prepared. Agents Forum one evening before end of review to explain changes (tba). Procedure notes to be prepared for all applicants and agents. Listing the process & identifying where information leaflets are required for various parties.
|
16. | Information Leaflets |  | Core list agreed and priorities identified. |
17. | RECORD SITE VISIT DATE
Separate Site Visit Record (see GP)
Ø internal target
Ø set out bigger picture
Ø presentation to staff | LN | Deferred pending new IT system |
18. | HISTORY TO 1974
a) Stop doing SCR3
b) Move start date | LN
ST/PH | COMPLETED
On hold pending consideration of risks. |
19. | CONSTRAINTS/INCONSISTENCIES
MAPINFO
ZONING/ZONES Check Policy | JF/LN |
Work in hand |
20. | SUMMARYSHEET/ALLOCATION PROCESS | GP/LN |
Deferred pending new IT system |
21. | CONSULTATION MANUAL | BT |
Preliminary draft prepared. Final version by mid May target not met. Documents now need to be tested by staff responsible for procedures and linked to new systems. |
22. | DELEGATED OUTPUTS
CONDITIONS | BT to co-ordinate | Revised list of conditions and reasons for refusal completed. |
23. | DESIGNATING DELEGATED vs COMMITTEE AT ALLOCATION ? | BT/LN |
Not met. To be done by end of May 2002.
|
24. | DELEGATED DECISION PROCESS | ST/BT |
Interim arrangements agreed at DC Procedure meeting on 13th March together with 24 - COMPLETED |
25. | INVOLVEMENT OF PPO IN COMMITTEE REPORTS | BT |
About Quality Control. Need to decide a suitable protocol to identify kind of reports PPO needs to see. END MAY. Target met
|
26. | S/S AGENDA – use style to page break – add footer with date |  |
COMPLETED |
27. | GOOD PRACTICE ON FILES | BT/LN |
Note has been circulated to staff but needs to be reinforced..
|
28. | P100 AND FILE NOTES | BT/LN |
Promote appropriate use of green pad – COMPLETED
Create link with MapInfo – END SEPTEMBER 2001 Target not met |
29. | CHECK ELECTRONIC ENFORCEMENT COMPLAINTS SYSTEMS & PREPARE FOR IMPLEMENTATION | LN/BT/DM |
Target end of May 2001. Interim arrangement implemented in October 200. Also see DC4 |
30. | RE-ORIENTATING THE ENFORCEMENT TEAM
Training Requirements:
1. Systems
2. Enforcement Case work | BT/GP |
Dependent on implementation of new IT System (see 29 above and DC 4) |
31. | WEEKLY MONITORING OF ENFORCEMENT (Management reporting of changes in cases) | BT/DA/DM |
APRIL ONWARDS. Not achieved. This needs to be addressed asap. |
32. | PREPARATION OF LEAFLET ON ENFORCEMENT
Brainstorming Session needed | BT |
AUGUST; Draft charter to be considered by Development Control in April 2002. |
33. | APPEALS PROGRESS SHEET
(weekly update) | BT/LN |
To review what there is in existence and whether new data base system is required. Also talk to SW and JG about requirements END JUNE Target not met. DCPM considering issue as part of wider organisational issues. |
34. | IDENTIFYING STAFF RESOURCES TO ADMINISTER APPEALS | BT/LN |
See 33 and wider organisational changes. |
35. | POLICY TOWARDS PREPARING APPEAL STATEMENT – Preparation of template & accompanying guidance note. | BT/APO |
Completed |
36. | MONITORING APPEAL DECISIONS - – both by DC and Policy
SUMMARY OF APPEAL DECISION TO GO TO COMMITTEE | BT/PH |
To determine how these processes should be handled. Monitoring to be built into new IT systems.
SEPTEMBER
Targets not met due to pressure on staff resources. DCPM considering solution as part of wider organisational issues.
|